| Background |
Occidental MukhaiznaOccidental Mukhaizna plans to develop its Occidental MukhaiznaOccidental Mukhaizna EOR project at the Mukhaizna oil field in Oman. The project consists of two packages: a wastewater recycling & reuse plant package and a central production processing facilities package. The project aims to increase oil production from 10,000 bpd to 150,000 bpd through thermal injection techniques. The project is intended to lift high viscosity and low permeability crude and to recover 1 billion barrels of heavy oil from Mukhaizna over the life of the project, from its present estimated reserves of 2 billion barrels. MEG Worley is the FEED study consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q3 2012 |
Completion | Wastewater recycling and reuse plant package expected to be completed
|
|
| Latest Events |
In January 2012, construction of the wastewater recycling and reuse plant package was ongoing. In Q3 2012, the wastewater recycling and reuse plant package is expected to be completed marking the completion of the overall project. |
| Previous Events |
In Q4 2008, the central production processing facilities package was completed. In Q1 2007, construction on the wastewater recycling and reuse plant package started. In Q4 2006, construction on the central production processing facilities package started. In September 2006, the EPC contract for the wastewater recycling and reuse plant package was awarded to Aquatech International Corporation and the EPC contract for the central production processing facilities package was awarded to Dodsal and Company. In August 2005, the FEED study contract was awarded to MEG Worley. In January 2005, bidders submitted their proposals for the FEED study contract. |
| Scope of Work |
Construction of : Wastewater recycling and reuse plant package Central production processing facility package: -Oil treatment unit -De-oiling train -Tank farm -De-sanding facilities -VRU compression system -Flare facilities -Utility systems |
| Contract Packages |
|
| Related Projects |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Jan 2005 |
FEED | Bidders submitted their proposals
|
| Aug 2005 |
FEED | Contract awarded to MEG Worley
|
| Sep 2006 |
EPC | Contract awarded to Aquatech for the wastewater recycling & reuse plant package | | | EPC | Contract awarded to Dodsal for the central production processing facilities package
|
| Q4 2006 |
EPC | Construction on the central production processing facilities package started
|
| Q1 2007 |
EPC | Construction on the wastewater recycling and reuse plant package started
|
| Q4 2008 |
Completion | Central production processing facilities package completed
|
| Q3 2012 |
Completion | Wastewater recycling and reuse plant package expected to be completed
|
|
|