| Country |
: |
UAE |
| Project Value |
: |
USD 2,100,000,000 Estimated |
| Sector |
: |
Oil and Gas | NGL |
|
Consultant |
: |
Fluor Mideast Limited
(Pre-feed and FEED) |
|
PMCs |
: |
KBR Middle East
(PMC for FEED) |
WorleyParsons Engineering
(Overseeing EPC) |
|
Contractor |
: |
Jv of Petrofac Limited and GS Engineering and Construction Company
(EPC) |
|
Sub-Contractors |
: |
Siemens
(Electrical Work) |
Target Engineering Construction Company
(Marine Work) |
| Profile Type |
: |
Contract Project
|
| Associated Projects |
: |
Contract (5) |
|
Phase: EPC - Execution
|
|
Completion: Q3 2013
|
|
|
|
| Background |
Abu Dhabi Gas Industries (Gasco)Abu Dhabi Gas Industries (Gasco) plans to build a fourth NGL train at Ruwais, Abu Dhabi. The package is part of of Abu Dhabi's Integrated Gas Development program which aims at increasing the offshore gas production by 1 billion cu.ft/d (high pressure gas). KBRKBR Leatherhead is the PMC overseeing the FEED study on the whole onshore part of the IGD program. FluorFluor Corporation is the pre-FEED study and FEED study consultant. WorleyParsonsWorleyParsons is the PMC overseeing the EPC contract. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
EPC | Marine works expected to be completed
|
| Q4 2012 |
Commissioning | Expected to start
|
| Q3 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, construction of the train and marine works were ongoing. In June 2012, the marine works are expected to be completed. In Q4 2012, commissioning is expected to start. In Q3 2013, the project is expected to be completed. |
| Previous Events |
In September 2010, construction execution was in progress. In July 2010, Siemens Energy Company was awarded a USD 40 million electrical subcontract. In March 2010, PetrofacPetrofac and GS Engineering and Construction awarded Target Engineering Construction CompanyTarget Engineering Construction Company a USD 130 million contract to execute the sea water intake system and pipeline for the project. On 29 October 2009, Gasco and the JV of PetrofacPetrofac and GS Engineering and Construction CompanyGS Engineering and Construction Company signed the official EPC contract. On 15 July 2009, the EPC contract was awarded to the JV of PetrofacPetrofac and GS Engineering and Construction CompanyGS Engineering and Construction Company . On 7 July 2009, commercial bids for the EPC contract were submitted. On 22 June 2009, the PMC for the EPC contract was awarded to WorleyParsonsWorleyParsons . 30 April 2009 was the technical bids submission deadline for the EPC contract (extended from 1 March 2009). 28 January 2009 was the commercial bids submission deadline for the PMC contract. In November 2008, technical bids for the PMC contract were submitted. In July 2008, the FEED study was completed and the ITB for the EPC contract was issued. On 3 May 2007, KBRKBR Leatherhead was awarded the PMC contract overseeing the FEED study contract. In December 2006, the ITB PMC contract overseeing FEED study contract was issued. In July 2006, the FEED study contract was awarded to FluorFluor . |
| Scope of Work |
Construction of an NGL recovery train. Scope of work for Siemens Energy includes: -Power and distribution transformers -High, medium, and low-voltage switch gears -Motor control centers -A power management system -Medium and low voltage motors |
| Contract Packages |
| Type |
Project Name |
Contract Value |
 |
Abu Dhabi Integrated Gas Development (IGD) |
USD 10,000,000,000 |
 |
ADGAS - IGD - Das Island Process Facilities and Utilities |
USD 1,000,000,000 |
 |
ADMA OPCO - IGD - Umm Shaif Gas Processing Platform |
USD 402,000,000 |
 |
Gasco - IGD - Habshan 5 Gas Processing Plant |
USD 4,700,000,000 |
 |
Gasco - IGD - Habshan 5 Offsites and Utilities |
USD 1,700,000,000 |
 |
Gasco - IGD - LPG Storage Tanks |
USD 534,000,000 |
|