| Background |
Kuwait National Petroleum CompanyKuwait National Petroleum Company (KNPCKNPC ) plans to build a flare gas recovery unit at U-01 and U-49 flare system, in Mina Abdullah Refinery, Kuwait. The project comprises a flare gas recovery facility, coolers, drums, piping works and separators. AmecAmec is the FEED study consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q4 2012 |
FEED | Study expected to be completed
|
| Mar 2013 |
EPC | ITB expected to be issued
|
| Q4 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, the FEED study was in progress. In Q4 2012, the FEED study is expected to be completed. In March 2013, the ITB for the EPC contract is expected to be issued. In Q4 2014, the project is expected to be completed. |
| Previous Events |
In the end of June 2011, the FEED study started. In Q1 2011, the FEED study contract was awarded to AmecAmec . In November 2010, bids for the FEED study contract were under evaluation. |
| Scope of Work |
Work includes the construction and installation of: - Flare gas recovery facility - Inter-stage coolers - A knockout drum - A compressor suction - Discharge coolers - A flare seal drum - Separators - Condensate pumps - Piping works - Civil works - A compressor shelter - Substation modification, electrical works, field Instrumentation and control system modifications |
|
| Schedule | Contract Phase/Phase | Description |
| Q1 2011 |
FEED | Contract awarded to AmecAmec
|
| Jun 2011 |
FEED | Study started
|
| Q4 2012 |
FEED | Study expected to be completed
|
| Mar 2013 |
EPC | ITB expected to be issued
|
| Q4 2014 |
Completion | Project expected to be completed
|
|
|