| Country |
: |
Qatar |
| Project Value |
: |
USD 7,000,000,000 Estimated |
| Sector |
: |
Infrastructure | Ports |
|
Consultants |
: |
Royal Haskoning
(Master Plan) |
Scott Wilson Kirkpatrick and Company Middle East
(Conceptual design) |
COWI A/S Qatar
(Technical) |
WorleyParsons Engineering
(Detailed design) |
|
PMC |
: |
AECOM
|
| Profile Type |
: |
Master Project
|
| Associated Projects |
: |
Contract (2) |
|
Phase: Construction - Execution
|
|
Completion: 2025
|
|
|
|
| Owner |
: |
The New Doha Port Steering Committee
|
| Location |
: |
Al Wakra, Doha, Qatar
|
| Contract Type |
: |
Construction |
| Facility Type |
: |
Port |
| Capacity |
: |
6 million TEU per year 20 sq.km. |
|
| Background |
The New Doha Port Steering Committee plans to build a new port in Economic Zone number 3, Al Wakra, south of Mesaieed area, Qatar. The New Doha Port will be developed in 3 phases. The new port will be linked to the mainland by an 8.5 Km long trestle bridge. Phase 3 will include a container terminal, berths, an administration and customs complex and a tug and pilot boats berth area. It will support the industrial development in the area and will be developed in phases to reach a final capacity of 6 million 20 TEU per year by 2030. The first phase of the project will give the port a capacity of 2 million 20 TEU per year. The existing Doha port is likely to be decommissioned due to the site's physical constraints on expansion projects. Scott Wilson Kirkpatrick and Company Middle EastScott Wilson Kirkpatrick and Company Middle East is the conceptual design consultant and is responsible for document preparation. Within the design, Scott Wilson Kirkpatrick and Company Middle EastScott Wilson Kirkpatrick and Company Middle East took into account that after 2030 the New Port might need to expand further to reach a capacity of 10 million 20TEU per year. Scott Wilson Kirkpatrick and Company Middle EastScott Wilson Kirkpatrick and Company Middle East is the conceptual design consultant. Worley ParsonsWorley Parsons is the detailed design consultant. Royal Haskoning is the master plan consultant. COWI A/S QatarCOWI A/S Qatar is the technical consultant. AECOMAECOM is the PMC. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jun 2012 |
Construction | Construction of phase 2 expected to start
|
| 2013 |
Design | Design of phase 3 expected to be completed
|
| Q3 2015 |
Completion | Phase 1 expected to be completed | | Q1 2016 | Completion | Phase 2 expected to be completed | | 2025 | Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, the mobilization works for phase 2 was ongoing. In June 2012, the construction of phase 2 is expected to start. In 2013, the design of phase 3 is expected to be completed. In Q3 2015, phase 1 is expected to be completed. In Q1 2016, phase 2 is expected to be completed. In 2025, the project is expected to be completed. |
| Previous Events |
In March 2012, design of the port was still ongoing; phase 1 was under construction and construction contract of phase 2 was awarded to Middle East Dredging Company. In November 2011, phase 1 was under construction and phase 2 was under bid evaluation. In August 2011, the ITB for the construction contract of phase 2 was issued. In July 2011, the design of the port and the construction of phase 1 were ongoing. In June 2011, the design of the port and the construction of phase 1 were ongoing. On 13 March 2011, the construction contract of phase 1 was signed with China Harbour Engineering Arabia CompanyChina Harbour Engineering Arabia Company . In January 2011, the construction contract of phase 1 was awarded to China Harbour Engineering Arabia CompanyChina Harbour Engineering Arabia Company . In May 2009, companies were invited to prequalify for the construction contract of phase 1. In February 2009, the Environmental Impact Assessment (EIA) contract was awarded to COWI. In January 2009, the ITB for the construction contract of phase 1 was issued. In November 2008, the USD 145 million PMC contract was awarded to AecomAecom and the USD 33 million detailed design contract was awarded to Worley ParsonsWorley Parsons . In February 2008, the prequalification of companies for the EPCM and design contracts started. In July 2007, the New Doha Port Steering Committee was established. In December 2004, the master plan study and the design were completed. |
| Scope of Work |
Construction of a commercial port including: Phase1: - Excavation of 58 million cu.m. (It will be used to build 8 km of quay wall and a 5 km long breakwater) - Dredging a sea channel that will link to the existing sea channel for Messaeid industrial city - A 2 million TEUs container terminal - A 15 m. deep approach channel to the port - An 8 to 13.5 m. deep harbor basin - General cargo berths - Emiri yachts Phase2: - A 2 million TEUs container terminal - An extension to the harbor basin Phase 3: - A 2 million TEUs container terminal - Berths - An administration and customs complex - A tug and pilot boats berth area Construction of a naval forces base Construction of a 8.5 km long trestle bridge |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Dec 2004 |
Study | Masterplan study and design completed
|
| Jul 2007 |
Planning | New Doha Port Steering Committee established
|
| Feb 2008 |
EPCM | Prequalification started | | | Design | Prequalification started
|
| Nov 2008 |
PMC | Contract awarded to AECOMAECOM | | | Design | Contract awarded to Worley ParsonsWorley Parsons
|
| Jan 2009 |
Construction | ITB for phase 1's contract issued
|
| Feb 2009 |
Study | Environmental Impact Assessment (EIA) contract awarded to COWI
|
| Jan 2011 |
Construction | Phase 1's contract awarded to China Harbour Engineering Arabia CompanyChina Harbour Engineering Arabia Company
|
| 13 Mar 2011 |
Construction | Phase 1's contract signed with China Harbour Engineering Arabia CompanyChina Harbour Engineering Arabia Company
|
| Mar 2011 |
Construction | Construction of phase 1 started
|
| Aug 2011 |
Construction | ITB for phase 2's contract issued
|
| Mar 2012 |
Construction | Phase 2 contract awarded to Middle East Dredging Company (MEDCO)
|
| Jun 2012 |
Construction | Construction of phase 2 expected to start
|
| 2013 |
Design | Design of phase 3 expected to be completed
|
| Q3 2015 |
Completion | Phase 1 expected to be completed
|
| Q1 2016 |
Completion | Phase 2 expected to be completed
|
| 2025 |
Completion | Project expected to be completed
|
|
|
Key:
Master Project
Package Project
Contract Project
|
|
 |