| Background |
The Royal Commission for Jubail and YanbuRoyal Commission for Jubail and Yanbu (RCJYRCJY ) plans to construct TS3 and TS6 in Jubail Industrial City in Saudi Arabia. The project includes the construction of freeways, expressways and other infrastructure facilities. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q2 2012 |
Completion | Project expected to be completed
|
|
| Latest Events |
In February 2012, the construction works were ongoing. In Q2 2012, the project is expected to be completed. |
| Previous Events |
On 9 July 2011, the construction contract was awarded to Mohammed Ali Al Swailem Group. On 11 May 2011, bidders submitted their bids for the construction contract. On 9 March 2011, the RFP for the construction contract was issued. |
| Scope of Work |
Construction of: - A 5.4 km, 6 lane TS-3 freeway/expressway on 2 m to 13 m high embankment - A 5.6 km, 6 lane TS-6 freeway on 2 m to 3 m high embankment - Embankments - A roadway base and sub-base - Asphalted concrete courses - Curbs and accessories - A full diamond interchange with ramps between new TS-3 and existing T-138 - A full cloverleaf interchange with ramps between new TS-3 and new TS-6 - A 3 span precast composite concrete overpass bridge to carry the TS-3 over the T-138 roads and adjacent pipeline corridor - 2 culverts over existing pipeline corridor to carry T-138 interchange ramps - 4 span precast composite concrete overpass bridge to carry the TS-3 over the T-130 road and adjacent railway row - 2 span precast composite concrete overpass bridge to carry the TS-3 over the T-112 road - 2 span post-tensioned concrete overpass bridge to carry the TS-3 over the TS-6 at new cloverleaf interchange at TS-3 and TS-6 - 2 span post-tensioned concrete underpass bridge to carry the T-145 over the TS-6 - A reinforced concrete box culvert on primary drainage channel on TS-3 route north of TS-6 - An un-reinforced concrete arch culvert to carry proposed Southern Road of Mutrafiah over new drainage channel - Demolition of two large reinforced concrete box drainage culverts - Site preparation earthworks and finished grading within the contract area boundary - Demolition of existing fencing and roadways |
|
| Schedule | Contract Phase/Phase | Description |
| 09 Mar 2011 |
Construction | RFP issued
|
| 11 May 2011 |
Construction | Bids submitted
|
| 09 Jul 2011 |
Construction | Construction contract awarded to Mohammed Ali Al Swailem Group
|
| Q2 2012 |
Completion | Project expected to be completed
|
|
|