OWSC - New Darsait Sewage Treatment Plant
Country : Oman
Project Value : USD 96,000,000 Estimated
Sector : Power and Water | Sewage Treatment
Consultant : KEO International Consultants (PMC)
Profile Type :  Standalone Project
Phase:
Developer DBO - Execution
Completion: Dec 2013
 
 
Owner : Haya WaterHaya WaterLoading... - Oman
Location :
Muttrah, Muscat, Oman
Contract Type : DBO - Design, Build, Operate
Facility Type : Sewage treatment plant
Capacity : 50,000 cu.m./d
Background Oman Wastewater Services Company (OWSC)Oman Wastewater Services Company (OWSC)Loading..., also known as Haya WaterHaya WaterLoading..., plans to build a new sewage treatment plant (STP) in Darsait, in Greater Muttrah province.

The purpose of the project is to serve the population of Darsait.

The plant will have a capacity of 50,000 cu.m./d. It will be built in two phases.

The new plant will be OWSC's second sewage treatment plant in Darsait. The first STP has a capacity of 20,000 cu.m./d.

The New Darsait STP is part of the Muscat Wastewater Scheme.

KEO International consultants is the PMC.
Expected Events
Schedule Contract Phase/Phase Description
Dec 2013 CompletionProject expected to be completed
Latest Events In May 2012, the construction of the sewage treatment plant was ongoing.

In December 2013, the project is expected to be completed.
Previous Events In April 2011, construction of the sewage treatment plant started.

In March 2011, the preliminary work started.

On 19 January 2011, the DBO contract was signed with the consortium of Cadagua and Galfar Engineering and ContractingGalfar Engineering and ContractingLoading....

On 31 October 2010, the DBO contract was awarded to the consortium of Cadagua and Galfar Engineering and ContractingGalfar Engineering and ContractingLoading....

In February 2010, the PMC contract was awarded to KEO International ConsultantsKEO International ConsultantsLoading....

On 27 January 2010, bidders submitted their proposals for the DBO contract. The bids submission deadline was previously delayed from 28 September 2009, 26 October 2009, 16 November 2009 to 7 December 2009.

On 5 August 2009, the ITB for the DBO contract was issued.

On 27 July 2009, bidders submitted their proposals for the PMC contract. This deadline was extended from 6 July 2009.

In May 2009, the ITB for the PMC contract for the new Darsait STP was issued.
Scope of Work Construction of a 50,000 cu.m./d sewage treatment plant.
Project News
03-Apr-2008 OWSC highlights significance of Muscat Wastewater Scheme - Oman Daily Observer

Project Schedule

ScheduleContract Phase/PhaseDescription
May 2009 PMCITB issued
27 Jul 2009 PMCBidders submitted their proposals
05 Aug 2009 DBOITB issued
27 Jan 2010 DBOBidders submitted their proposals
Feb 2010 PMCContract awarded to KEO International ConsultantsKEO International ConsultantsLoading...
 
Bidders Awarded
31 Oct 2010 DBOContract awarded to the consortium of Cadagua and Galfar Engineering and ContractingGalfar Engineering and ContractingLoading...
19 Jan 2011 DBOContract signed with the consortium of Cadagua and Galfar Engineering and ContractingGalfar Engineering and ContractingLoading...
Mar 2011 DBOPreliminary work started
Apr 2011 DBOConstruction started
Dec 2013 CompletionProject expected to be completed

Project News

03-Apr-2008 OWSC highlights significance of Muscat Wastewater Scheme - Oman Daily Observer
 
Haya Water
Owner 
Haya Water Building, Al Ansab Area, P.O. Box 1047, Muscat 133, Oman, Muscat
Tel: +968 24-116100 | Fax: +968 24-115717 | Email: customerservice@haya.com.om | Website: http://www.haya.com.om
 
Al Sibakh House Ruwi, P.O. Box 2871, Oman
Tel: +968 24-478-306 | Fax: +968 24-480-849 | Website: http://www.keoic.com
  • Name: Al. Gullin
    Position: Project Director
    Email alg@keoic.com
 
Consortium of Cadagua and Galfar Engineering and Contracting
Developer - DBO
Building 760, Al Omaran Street, Ghala Industrial Area, P.O. Box 533, Muscat 100, 100, Oman
Tel: +968 24-591055,+968 24-525000 | Fax: +968 24-591676 | Email: galfar@omantel.net.om,galfarmail@galfar.com | Website: www.galfar.com
  • Name: Anil Arkheya
    Position: Project Manager
    Tel: +968 24-525000 ext:4420
Cadagua
Gran V?a 45 Street, Bilbao, Spain
Tel: +34 94-481-7300 | Fax: +34 94-481-7361 | Email: cadagua.info@cadagua.es | Website: http://www.cadagua.es