Saudi Arabia MWE - Al Ha'ir Wastewater Treatment Plant - Phase 2
Country : Saudi Arabia
Project Value : USD 450,000,000
Sector : Power and Water | Water Treatment
Consultants : ILF Consulting Engineers (Feasibility study) |  Fichtner Consulting Engineers (Technical)
Profile Type :  Contract Project
Associated Projects : Contract (1)
Delayed
Last Activity:
Developer BOO - Prequalification
Initial Completion: 2011
 
 
Owner : Ministry of Water and Electricity - Saudi ArabiaMinistry of Water and Electricity - Saudi ArabiaLoading... - Saudi Arabia
Location :
Riyadh , Saudi Arabia
Development Type : BOO
Facility Type : Wastewater treatment plant
Capacity : 400,000 cu.m./d.
Background The Ministry of Water and ElectricityMinistry of Water and ElectricityLoading... plans to construct Phase 2 of the wastewater treatment plant in Al Ha'ir in the Central province.

The project is part of Riyadh's wastewater privatisation programme that aims to increase the treatment capacity from 700,000 cu.m/d. to 2.3 million cu.m./d. by 2022.

ILF Consulting Engineers carried is the feasibility study consultant and Fichtner Consulting Engineers is the technical advisor for the project.
Expected Events
Schedule Contract Phase/Phase Description
H2 2011 PlanningDecision to shift project from BOO to EPC expected to be taken
Latest Events In July 2011, the negotiations to shift the project from a BOO to an EPC basis were ongoing.

In H2 2011, a decision to shift the project from a BOO to an EPC basis is expected to be taken. The project was initially expected to be completed in 2011.
Previous Events In July 2010, National Water CompanyNational Water CompanyLoading... was negotiating with the Ministry of Water and ElectricityMinistry of Water and ElectricityLoading... to shift the project from BOO contract into an EPC basis.

In March 2009, the RFQ and RFP were under final revision and National Water CompanyNational Water CompanyLoading... was seeking for credit support from the Ministry of FinanceMinistry of FinanceLoading....

In Q4 2007, the feasibilty study was completed.

In July 2006, the feasibility study contract awarded to ILF Consulting Engineers.
Scope of Work Construction of a 400,000 cu.m./day waste water treatment plant and associated works.
Financing Source HSBCHSBCLoading... is the financial advisor and Clifford ChanceClifford ChanceLoading... is the legal advisor.
Contract Packages
Type Project Name Contract Value
Saudi Arabia MWE - Al Kharj Wastewater Treatment Plant Expansion (Phase 2) -
Project News
24-Jul-2007 Details on Riyadh Waste Water Treatment Plants - Arab News
03-Aug-2006 Saudi Arabia Ministry of Water and Electricity signs SR23.4mprivatisation contracts - Khaleej Times
23-Jul-2006 Saudi Arabia: Water Ministry Signs 5 Consultancy Deals - Arab News
» More News

Project Schedule

ScheduleContract Phase/PhaseDescription
Jul 2006 StudyFeasibility study contract awarded to ILF Consulting Engineers
Q4 2007 StudyFeasibilty study was completed
H2 2011 PlanningDecision to shift project from BOO to EPC expected to be taken

Project News

24-Jul-2007 Details on Riyadh Waste Water Treatment Plants - Arab News
03-Aug-2006 Saudi Arabia Ministry of Water and Electricity signs SR23.4mprivatisation contracts - Khaleej Times
23-Jul-2006 Saudi Arabia: Water Ministry Signs 5 Consultancy Deals - Arab News
 
Saud Mall Center, Ministry of Water and Electricity Building, King Fahed Road, Mohammadiah Area, Riyadh 11233, Saudi Arabia, Riyadh
Tel: +966 1-203-8888,+966 1-205-2981,+966 1-404-0180 | Fax: +966 1-205-0557,+966 1-205-2748 | Email: info@mowe.gov.sa | Website: www.mowe.gov.sa
  • Name: Majed Al Rouwaili
    Position: Project Engineer
    Tel: +966 1-203-8888 ext:2763
 
ILF Consulting Engineers
Consultant - Feasibility study
Al Ferdous Building, 4th floor, Salam Street, Abu Dhabi, P.O. Box 73250, Abu Dhabi, UAE
Tel: +971 2 671-6500 | Fax: +971 2 671- 6166 | Email: info@adb.ilf.com | Website: http://www.ilf.com
  • Name: Issam Saleh
    Position: Project Engineer
    Tel: +966 1-465-4145 ext:420
    Fax: +966 1-464-4616
    Email ilfruh@sps.net.sa
 
Fichtner Consulting Engineers
Consultant - Technical
Riyadh, P.O. Box 6741, Riyadh 11452, Saudi Arabia
Tel: +966 1-463-2547 | Fax: +966 1-461-2602 | Website: www.fichtner.co.uk
Key:    Master Project    Package Project    Contract Project