Connecting intelligence with intelligence

×

Projects Monitor 

Covering major construction projects in the Middle East
Updated: 23May12
 
JRSP - Jordan Red Sea Project - Phase 1
Also Known As : JRSP Phase 1
Country : Jordan
Project Value : USD 4,500,000,000
Sector : Power and Water | Water Desalination
Profile Type :  Contract Project
Phase:
Developer BOT - Bid Evaluation
Completion: 2015
 
 
Owner : Jordan Red Sea Project
Location :
Al Aqabah, Al Aqaba , Jordan
Development Type : BOT
Facility Type : Desalination plant
Capacity : 200 million cu.m./y
Background The Jordan Red Sea Project Company, with the support of the Jordanian Ministry of Water and IrrigationMinistry of Water and IrrigationLoading..., plans to develop the first phase of the Jordan Red Sea Project.

The desalinated water produced will be used to serve Aqaba and development projects in the area.

The project consists of the extraction of 400 million cu.m/y of sea water from the Red Sea and its transportation through a pipeline to the two desalination plants in Aqaba and in the Dead Sea region. The desalination plant will have a total capacity of 200 million cu.m./y. The Aqaba desalination plant will produce 50 million cu.m./y of desalinated water. The remaining capacity (150 million cu.m./y) will be built near the Dead Sea (exact location to be determined). Excess sea water and desalination brine will be discharged into the Dead Sea.

This project consists of the first phase of the five-phased Jordan Red Sea project. The other phases will be developed gradually depending on the re-assessment of water demand. The master project is expected to generate 900 million cu.m./y of desalinated water and will be completed within 30 years.
Expected Events
Schedule Contract Phase/Phase Description
Q2 2012 BOTContract expected to be awarded
2015 CompletionProject expected to be completed
Latest Events In May 2012, bids for the BOT contract were under evaluation.

In Q3 2012, the BOT contract is expected to be awarded.

In 2015, the project is expected to be completed.
Previous Events On 31 January 2012, bidders submitted their proposals for the BOT contract.

At the end of April 2011, the RFP for the BOT contract was issued.

On 1 April 2011, six companies were pre-qualified for the BOT contract.

On 1 March 2011, companies submitted their pre-qualification documents for the BOT contract (previously expected in February 2011).

In November 2010, the RFQ for the BOT contract was issued.

In February 2010, 29 companies submitted their EOIs for the project.

In November 2009, companies were invited to submit their EOIs for the Master Developer contract (PPP).
Scope of Work Construction of a:
-desalination plant with a capacity of 50 million cu.m./y
-desalination plant with a capacity of 150 million cu.m./y
-water pipeline with a capacity of 400 million cu.m./y
Contract Packages
Type Project Name Contract Value
JRSP - Jordan Red Sea Project USD 10,000,000,000

Project Schedule

ScheduleContract Phase/PhaseDescription
Nov 2009 BOTInvitation for the EOIs submission issued
Feb 2010 BOTCompanies submitted their EOIs
Nov 2010 BOTRFQ issued
01 Mar 2011 BOTCompanies submitted their pre-qualification documents
01 Apr 2011 BOTSix companies pre-qualified
Apr 2011 BOTRFP issued
31 Jan 2012 BOTBids submission deadline
 
Prequalified Bidders
Q2 2012 BOTContract expected to be awarded
2015 CompletionProject expected to be completed
 
Jordan Red Sea Project
Owner 
Arabtech Jardaneh No 8 Building, Al Tabasheer 3 Street, Jordan
Tel: +962 6-581-7073 | Website: http://www.jrsp-jordan.com/
 
Ministry of Water and Irrigation Building, Shmeisani Area, P.O. Box 2412, Amman 5012, Jordan, Capital Governorate
Tel: +962 6-568-0100 | Fax: +962 6-568-0075 | Email: info@mwi.gov.jo | Website: www.mwi.gov.jo
  • Name: Fayez Al Batayli
    Position: Public Relations
    Tel: +962 79-551-5110