| Background |
The Jordan Red Sea Project Company, with the support of the Jordanian Ministry of Water and IrrigationMinistry of Water and Irrigation , plans to develop the first phase of the Jordan Red Sea Project. The desalinated water produced will be used to serve Aqaba and development projects in the area. The project consists of the extraction of 400 million cu.m/y of sea water from the Red Sea and its transportation through a pipeline to the two desalination plants in Aqaba and in the Dead Sea region. The desalination plant will have a total capacity of 200 million cu.m./y. The Aqaba desalination plant will produce 50 million cu.m./y of desalinated water. The remaining capacity (150 million cu.m./y) will be built near the Dead Sea (exact location to be determined). Excess sea water and desalination brine will be discharged into the Dead Sea. This project consists of the first phase of the five-phased Jordan Red Sea project. The other phases will be developed gradually depending on the re-assessment of water demand. The master project is expected to generate 900 million cu.m./y of desalinated water and will be completed within 30 years. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q2 2012 |
BOT | Contract expected to be awarded
|
| 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In May 2012, bids for the BOT contract were under evaluation. In Q3 2012, the BOT contract is expected to be awarded. In 2015, the project is expected to be completed. |
| Previous Events |
On 31 January 2012, bidders submitted their proposals for the BOT contract. At the end of April 2011, the RFP for the BOT contract was issued. On 1 April 2011, six companies were pre-qualified for the BOT contract. On 1 March 2011, companies submitted their pre-qualification documents for the BOT contract (previously expected in February 2011). In November 2010, the RFQ for the BOT contract was issued. In February 2010, 29 companies submitted their EOIs for the project. In November 2009, companies were invited to submit their EOIs for the Master Developer contract (PPP). |
| Scope of Work |
Construction of a: -desalination plant with a capacity of 50 million cu.m./y -desalination plant with a capacity of 150 million cu.m./y -water pipeline with a capacity of 400 million cu.m./y |
| Contract Packages |
|
|
| Schedule | Contract Phase/Phase | Description |
| Nov 2009 |
BOT | Invitation for the EOIs submission issued
|
| Feb 2010 |
BOT | Companies submitted their EOIs
|
| Nov 2010 |
BOT | RFQ issued
|
| 01 Mar 2011 |
BOT | Companies submitted their pre-qualification documents
|
| 01 Apr 2011 |
BOT | Six companies pre-qualified
|
| Apr 2011 |
BOT | RFP issued
|
| 31 Jan 2012 |
BOT | Bids submission deadline
|
| Q2 2012 |
BOT | Contract expected to be awarded
|
| 2015 |
Completion | Project expected to be completed
|
|