| Owner |
: |
Ruwais Fertilizer IndustriesRuwais Fertilizer Industries - UAE
|
| Location |
: |
Ruwais, Abu Dhabi, UAE
|
| Contract Type |
: |
EPC - Engineering, Procurement, Construction |
| Payment Terms |
: |
Lump Sum Turnkey (LSTK) |
| Facility Type |
: |
Fertilizer complex |
| Capacity |
: |
2,000 t/d Ammonia 3,500 t/d Urea |
|
| Background |
Ruwais Fertilizer IndustriesRuwais Fertilizer Industries (FertilFertil ) plans to expand the fertilizer complex in Ruwais, west of Abu Dhabi. The plant will have a capacity of 2,000 t/d of ammonia and 3,500 t/d of urea. Gas feedstock will be supplied from the GascoGasco operated Asab, Bab and Thamama C fields. Jacobs EngineeringJacobs Engineering is the feasibility study consultant. UhdeUhde is the technology licensor for the plant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Jan 2013 |
Commissioning | Commissioning of the facilities expected to start
|
| Q1 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In December 2011, construction of the facilities was ongoing. In January 2013, commissioning of the facilities is expected to start. In Q1 2013, the project is expected to be completed. |
| Previous Events |
In December 2010, main construction of the facilities started. In October 2010, engineering works were in progress. In October 2009, the engineering, procurement, construction and commissioning contract was awarded to Samsung EngineeringSamsung Engineering and Construction Company. On 7 September 2009, bidders submitted their commercial proposals for the EPC and technology contract (delayed for the second time from July 2009). On 18 December 2008, bidders submitted their technical proposals for the EPC contract. In August 2008, four companies were prequalified for the EPC contract. In 2007, the project was being reconsidered by the shareholders. FertilFertil invited shortlisted companies to submit expressions of interest for the combined FEED and EPC contract. |
| Scope of Work |
Construction of a 2,000 t/d Ammonia and a 3,500 t/d Urea facilities. |
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Aug 2008 |
EPC | Companies prequalified
|
| Dec 2008 |
EPC | Bidders submitted their technical proposals
|
| 07 Sep 2009 |
EPC | Bidders submitted their commercial proposals
|
| Oct 2009 |
EPC | Contract awarded to Samsung EngineeringSamsung Engineering and Construction Company
|
|
|
- Samsung Engineering and Construction
|
|
| Dec 2010 |
EPC | Main construction of the facilities started
|
| Jan 2013 |
Commissioning | Commissioning of the facilities expected to start
|
| Q1 2013 |
Completion | Project expected to be completed
|
|
|