| Background |
The Ministry of Transport and CommunicationThe Ministry of Transport and Communication plans to construct Al Duqm Airport in Al Wusta, Oman. Al Duqm Airport will be executed in 3 packages. Package 1 includes the construction of roadways and utilities. Package 2 includes the construction of the runways and airfield infrastructure and package 3 involves the construction of the terminal buildings and other buildings on the site. Aeroports de Paris Ingenierie (ADPi) is the PMC. Ibn Khaldun Almadaen Engineering ConsultantsIbn Khaldun Almadaen Engineering Consultants is the supervision and management consultant. Parsons InternationalParsons International is the design consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q4 2013 |
Completion | Project expected to be completed
|
|
| Latest Events |
In April 2012, packages 1 and 2 were under construction and bids for package 3 were still under evaluation. In Q4 2013, the project is expected to be completed. |
| Previous Events |
In October 2011, packages 1 and 2 were under construction and package 3 was under bid evaluation. In January 2011, the ITB for the construction contract of package 3 was issued and the construction of package 2 started. In December 2010, the construction contract of package 2 was awarded to Hanjin Heavy Industries and Construction. In Q4 2009, the supervision and management consultancy contract was awarded to Ibn Khaldun Almadaen Engineering ConsultantsIbn Khaldun Almadaen Engineering Consultants . On 18 August 2009, the ITB for the construction contract of package 2 was issued. On 11 May 2009, bidders submitted their proposals for the supervision and management consultancy contract. On 3 March 2009, the ITB for the supervision and management consultancy contract was issued. In November 2008, the construction of package 1 started. In September 2008, the construction contract of package 1 was awarded to Desert Line ProjectsDesert Line Projects . In March 2008, the design for package 1 was completed. In December 2006, the design consultancy contract was awarded to Parsons InternationalParsons International . |
| Scope of Work |
Construction of an airport including: - 13,350 sq. m. parking facility for handling 300 cars - A 4 km long runway - A 500,000 passengers per year terminal - A 50,000 tonnes per year cargo terminal - A catering facility - A 27 km of access and land side roads - 2 taxiways - Parking apron for passenger aircraft - Facilities for 2 passenger boarding bridges |
| Contract Packages |
|
| Project News |
|
|
| Schedule | Contract Phase/Phase | Description |
| Dec 2006 |
Design | Contract awarded to Parsons InternationalParsons International
|
| Mar 2008 |
Design | Design for package 1 completed
|
| Sep 2008 |
Construction | Contract of package 1 awarded to Desert Line ProjectsDesert Line Projects
|
| Nov 2008 |
Construction | Construction of package 1 started
|
| 03 Mar 2009 |
Consultant | ITB for supervision and management consultancy contract issued
|
| 11 May 2009 |
Consultant | Bidders submitted their proposals
|
| 18 Aug 2009 |
Construction | ITB for contract of package 2 issued
|
| Q4 2009 |
Consultant | Contract awarded to Ibn Khaldun Almadaen Engineering ConsultantsIbn Khaldun Almadaen Engineering Consultants
|
| Dec 2010 |
Construction | Contract of package 2 awarded to Hanjin Heavy Industries and Construction
|
| Jan 2011 |
Construction | ITB for contract of package 3 issued | | | Construction | Construction of package 2 started
|
| Q4 2013 |
Completion | Project expected to be completed
|
|
|