Updated: 22Feb12
 
ONE - Tarfaya Wind Farm
Country : Morocco
Project Value : USD 352,000,000
Sector : Power and Water | Power Generation
Alternative Energy | Wind Energy
Consultant : Garrad Hassan (Technical)
Contractor : Jv of International Power and Nareva Holding (EPC)
Profile Type :  Standalone Project
Associated Projects :  | Related Projects (7)
Phase:
EPC - Execution
Completion: Q4 2013
 
 
Owner : Office National de l'ElectricitéOffice National de l'ElectricitéLoading... - Morocco
Location :
Tarfaya, Oued El-Dahab-Lagouira, Morocco
Contract Type : EPC - Engineering, Procurement, Construction
Facility Type : Wind farm
Capacity : 300 MW
Background The Office National de l'Electricité (ONE)Office National de l'Electricité (ONE)Loading... plans to build a wind power plant in Tarfaya, Morocco.

The purpose of the project is to meet the increasing national electricity demand.

Garrad Hassan is the technical consultant.
Expected Events
Schedule Contract Phase/Phase Description
Q4 2013 CompletionProject expected to be completed
Latest Events In March 2012, the power purchase agreement (PPA) was signed between ONE and JV of International PowerInternational PowerLoading... and Nareva Holding and construction started.

In Q4 2013, the project is expected to be completed.
Previous Events In March 2012, the power purchase agreement (PPA) is expected to be signed and construction is expected to start (delayed from Q4 2011).

In May 2011, negotiations with the JV of International PowerInternational PowerLoading... and Nareva Holding were in progress.

In August 2010, ONE awarded the EPC contract to the JV of International PowerInternational PowerLoading... and Nareva Holding as EPC contractor.

In July 2009, bidders submitted their proposals for the EPC contract.

In February 2008, the RFP for the EPC contract was issued.
Scope of Work Construction of a 300 MW wind power plant.
Financing Source HSBCHSBCLoading... is the financial adviser. Chadbourne and Parke is the legal adviser.
Related Projects

Project Schedule

ScheduleContract Phase/PhaseDescription
Feb 2008 EPCRFP issued
Jul 2009 EPCBidders submitted their proposals
Aug 2010 EPCContract awarded to the JV of International PowerInternational PowerLoading... and Nareva Holding
 
Bidders Awarded
  • Jv of International Power and Nareva Holding
Mar 2012 EPCPPA signed and construction started
Q4 2013 CompletionProject expected to be completed
 
Office National de l'Electricité Building, Othman Ben Affane Street, P.O. Box 13498, Casablanca 20000, Morocco, Greater Casablanca
Tel: +212 522-668080 | Fax: +212 522-220038 | Email: one@one.org.ma | Website: http://www.one.org.ma
  • Name: Mounia Jarir
    Position: Corporate Communication Manager
    Tel: +212 522-668471
  • Name: Chaguer Latifa
    Position: Project manager
    Tel: +212 522-668040
 
Garrad Hassan
Consultant - Technical
Maadi Zahret El-Maadi Tower, 35th floor, 66 Cornich El-Nile Street, Cairo, Cairo 11431, Egypt
Tel: +20 2-2528-7295 | Fax: +20 2-2528-7294 | Website: http://www.gl-garradhassan.com/
 
Jv of International Power and Nareva Holding
Contractor - EPC
Nareva Holding
Morocco
Abu Dhabi, United Arab Emirates
Print
 
  • SEARCH MIDDLE EAST PROJECTS
 
 
 
 
Panel