| Background |
Zakum Development CompanyZakum Development Company (ZadcoZadco ) plans to build gas processing plants at its upper Zakum field, in Abu Dhabi. This package is part of the overall development program that aims at increasing the production capacity from 550,000 to 750,000 bpd of oil by 2015. TechnipTechnip is the FEED study consultant. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| Q3 2012 |
EPC | Commercial bids expected to be submitted | | Q4 2012 | EPC | Contract expected to be awarded
|
| 2015 |
Completion | Project expected to be completed
|
|
| Latest Events |
In March 2012, technical bids for the EPC contract were submitted. In Q3 2012, commercial bids for the EPC are expected to be submitted. In Q4 2012, the EPC contract is expected to be awarded. In 2015, the project is expected to be completed. |
| Previous Events |
In October 2011, the ITB for the EPC contract was issued. In August 2011, the FEED study was completed. In May 2011, the FEED study started. On 29 March 2011, the FEED study contract was awarded to TechnipTechnip . |
| Scope of Work |
Construction of gas processing plants including: - A gas separation unit - A gas lift compression unit - A booster gas compression station - A power generation station - Offsites and utilities - Interconnecting pipelines - Modification of existing facilities Installation of water separation and disposal facilities at the existing satellite production platforms |
| Contract Packages |
| Type |
Project Name |
Contract Value |
 |
ZADCO - Upper Zakum Full Field Development |
USD 15,000,000,000 |
 |
ZADCO - Upper Zakum Full Field Development - Dredging Package |
USD 635,000,000 |
 |
ZADCO - Upper Zakum Full Field Development - East Area Development 8276 (Topside Modification) |
- |
 |
ZADCO - Upper Zakum Full Field Development - Main Oil Line |
USD 300,000,000 |
 |
ZADCO - Upper Zakum Full Field Development - Offshore Pipelines and Early Production Facilities |
USD 600,000,000 |
 |
ZADCO - Upper Zakum Full Field Development - Offshore Produced Water Facilities |
USD 50,000,000 |
|
|
| Schedule | Contract Phase/Phase | Description |
| 29 Mar 2011 |
FEED | Contract awarded to TechnipTechnip
|
| May 2011 |
FEED | Study started
|
| Aug 2011 |
FEED | Study completed
|
| Oct 2011 |
EPC | ITB issued
- JGC Corporation
- JV of NPCC and Technip
- JV of Tecnicas Reunidas and Saipem
- Jv of KBR and Hyundai Heavy Industries
- Jv of Petrofac Limited and Daewoo Shipbuilding and Marine Engineering Company
- Jv of Samsung Engineering Company and Sinopec
|
|
| Mar 2012 |
EPC | Technical bids submitted
|
| Q3 2012 |
EPC | Commercial bids expected to be submitted
|
| Q4 2012 |
EPC | Contract expected to be awarded
|
| 2015 |
Completion | Project expected to be completed
|
|
|