| Background |
The Royal Commission for Jubail and YanbuThe Royal Commission for Jubail and Yanbu (RCJYRCJY ) plans to build a feedstock and fuel pipelines network in Jubail Industrial City to serve the second stage development of Jubail 2. The project aims at transferring fuel into new facilities being built at Jubail 2. |
| Expected Events |
| Schedule |
Contract Phase/Phase |
Description |
| 07 Apr 2012 |
Construction | Bids submission deadline for the Procurement and Construction contract | | Q2 2012 | Construction | Procurement and Construction contract expected to be awarded
|
| Q3 2014 |
Completion | Project expected to be completed
|
|
| Latest Events |
In the beginning of February 2012, the ITB for the Procurement and Construction contract was issued. 7 April 2012 is the bids submission deadline for the Procurement and Construction contract. In Q2 2012, the Procurement and Construction contract is expected to be awarded. In Q3 2014, the project is expected to be completed. |
| Previous Events |
In H2 2011, engineering work was completed in-house. In H1 2011, the project was announced. |
| Scope of Work |
The project includes the construction of: - 36 inch in diameter carbon steel pipes for the methane and ethane gas extending from the end of Stage 1 to Stages 2 - Scraping facilities - Electrical buildings - Leak detection system - Distributed control system - Emergency shutdown system - Fiber optic network - Dedicated fuel gas and feedstock pipeline corridor' - Steel and concrete pipe support structures - Concrete structures - Concrete culverts and all associated work |
|
| Schedule | Contract Phase/Phase | Description |
| H1 2011 |
Announcement | Project launched
|
| H2 2011 |
Design | Engineering work completed in-house
|
| Feb 2012 |
Construction | ITB for the Procurement and Construction contract issued
|
| 07 Apr 2012 |
Construction | Bids submission deadline for the Procurement and Construction contract
|
| Q2 2012 |
Construction | Procurement and Construction contract expected to be awarded
|
| Q3 2014 |
Completion | Project expected to be completed
|
|