| 25 Aug 2010 |
|
Dewa to complete Dh450m project by February 2011
- Text size
DUBAI -- Dubai Electricity and Water AuthorityDubai Electricity and Water Authority
, or DewaDewa
, is making significant progress in the main water pipeline project. The Dh450 million project is likely to be completed by February next, a top official said
on Tuesday. "We have completed 48.458 kilometres of water pipelines until this date, accounting for 82.21 per cent. The work on the project, which aims to increase the capacity of water networks, began on June 15th, 2008, and we expect the completion of the works by February 14, 2011, " Saeed Mohammed Al Tayer, Managing Director and Chief Executive Officer of DewaDewa
.
continues to successfully move forward in the implementation of vital
infrastructure projects."We seek to raise productivity and operational efficiency, thus advancing the process of sustainable development in Dubai," Al Tayer said in a statement to Khaleej Times.
DewaDewa
's efforts come in the context of strengthening the water transmission networks and increasing the amount of water flow to meet the rapid growth in various locations of Dubai. The project, which aimed at supplying and extending water networks with a total length up to 59 kilometres, witnessed a significant progress in last three years."The project includes water transport pipelines with 1,200mm in diameter with an estimated total cost of Dh450 million. The areas covered by the project are along the Emirates from Diamond crossing up to Nad Al Hamr with a 59-kilometre length serving Al Barsha South, Wadi Al Safa, Nad Al Sheba , Ras Al Khor and Nad Al Hamr, " Al Tayer explained.
It is pertinent to note here that the production capacity of water desalination in DewaDewa
rose in 2009 to 330 million gallons per day, compared with 275 million gallons per day in the year 2008. Last week, the authority said it has commissioned two units of the Dh1.15 billion power generation and water desalination plant, M Station -- the biggest so far that can generate 2,000 megawatts electricity and 140 gallons of desalinated water per. By Muzaffar Rizvi
© Khaleej Times 2010
Zawya is a distributor (and not a publisher) of content supplied by third parties and subscribers. Any opinions, advice, statements, services, offers, or other information or content expressed or made available by those third parties, including information providers, subscribers or other users of the Service, are those of the respective author(s) or distributor(s) and not of the Company. The Company neither endorses nor is responsible for the accuracy or reliability of any opinion, advice or statement made on the Service by anyone other than authorized Service employee spokespersons while acting in their official capacities. The Company is not responsible for any infringement of intellectual property rights or breach of any applicable law or regulation, including regulation in relation to financial services or the distribution of financial products, defamation, data protection, telecommunications (including regulations relating to excessive use, spamming or other abusive activities) or obscene, offensive or illegal content). Under no circumstances will the Company be liable for any loss or damage caused by a member's reliance on information obtained through the Service. It is the responsibility of member to evaluate the accuracy, completeness or usefulness of any information, opinion, advice or other content available through the Service. Please seek the advice of professionals, as appropriate, regarding the evaluation of any specific information, opinion, advice or other content.
Read the full Member Agreement
http://www.zawya.com/legal/NewsLetter.cfm?name=disclaimer







Loading ...
Post a Comment
1.1 Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
1.2 Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
1.3 Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
1.4 Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
1.5 Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
1.6 Give the impression that they represent Zawya.
1.7 Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse.