Delays Start to Plague Giant Saudi Downstream Projects as Ras Tanura and PetroRabigh Plants Slip Behind

Press Release
 
 
22 September 2008
Two of Saudi Arabia's largest ongoing petrochemical projects, the US$10.1-billion PetroRabighPetroRabighLoading... joint venture (JV) with Japan's Sumitomo and the Saudi Aramco and Dow ChemicalDow ChemicalLoading... US$25-billion project at Ras Tanura, are facing mounting costs and delays, Middle East Economic Survey (MEES) reports. The scale of the projects, as well as global constraints on parts, materials, and experienced workforce are the main culprits, the report says, although the threat of a dearth of global project finance has also been highlighted. KBR, which last year was independently awarded the front end engineering and design (FEED) contract for the giant Ras Tanura project, has now been relieved of around 2 million man-hours of work from its vast contract due to overstretch, in a move to retake the initiative, although the resulting award process is likely to aggravate delays initially.

The Ras Tanura petrochemical project was initially budgeted at US$22 billion. PetroRabighPetroRabighLoading... is also experiencing delays, although it is now in the last phases of construction: its planned start-up was moved from late October to the first quarter of 2009. A proposed second-stage capacity-doubling project has been discussed, but any decision seems to have been put off until the worldwide market upheavals subside and the future becomes clearer, MEES said.

Significance: Saudi projects could be regarded as safe, as the financial muscle of state-owned giant Saudi Aramco virtually guarantees the financing of these politically important projects. Nevertheless the delays and soaring costs will add significant inconvenience to all parts in a market where growth is evaporating and future demand levels, as well as investments, become increasingly uncertain. Both Saudi projects are part of the job-creating strategies of the government, aiming to be centrepieces for industrialisation in the country. Hence they are aiming to attract private investment using their products as feedstock, a plan which--if project finance continues to dry up--could fail. This uncertainty is likely to lower the Saudi pace on starting new projects, despite the kingdom's capacity to fund them fully from its own deposits.

-Ends-

© Press Release 2008

 
 
 
Community Comments (0) - Comment on this article
The opinions of the authors expressed herein do not necessarily state or reflect Zawya. Read our Comment Policy.
 
 
 
Loading ...
 
Report Abuse
Loading ...
 
 
Loading ...
Zawya Comment Policy:
 
  1. Zawya encourages you to add a comment to this discussion. You agree that when you add content to this discussion your comments will not:
    1.1   Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
    1.2   Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
    1.3   Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
    1.4   Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
    1.5   Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
    1.6   Give the impression that they represent Zawya.
    1.7   Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse.
  2. The content posted on www.zawya.com is created by members of the public. The views expressed are theirs and unless specifically stated are not those of Zawya. Zawya reserves the right to review all comments prior to posting and edit or delete any contribution, but Zawya is not responsible for and can not be held liable for any content posted by members of the public on www.zawya.com.
  3. Zawya is not responsible for the availability or content of any third party sites that are accessible through www.zawya.com. Any links to third party websites from www.zawya.com do not amount to any endorsement of that site by Zawya and any use of that site by you is at your own risk.
  4. By submitting your comment, you hereby give Zawya the right, but not the obligation, to post, air, edit, exhibit, telecast, webcast, re-use, publish, reproduce, use, license, print, distribute or otherwise use your comments worldwide, in perpetuity.
 
 
 
 
 
 
 
Post Your Tender Notices for FREE
(No Sign-in Required)
 
 
Oil and Gas Tenders Due Date
IMPLEMENTATION OF MISC. PLANT CHANGE REQUESTS(PCRS) at HALUL 15Nov09
Provision of Catering Services and Related Services for KPC Employees Training Program - KUWAIT PETROLEUM CORPORATION 01Dec09
Installation, Operation & Maintenance of Integrated Security System for all company facilities consisting of Two Parts, Part A: Installation and Part B: Provision of Support, Operation & Maintenance 27Nov09
UPGRADE OF UPS SYSTEMS,BATTERY CHARGERS&BATTERY BANKS AT NFA 29Nov09
HOOK UP OF FLOWLINE,PWI & GASLIFT WELLS 13Dec09
PROVISION OF FUEL & MAINT OF FUEL OUTLETS (Tentative Bid Due Date and award date) 28Jan10
Qarn Alam Power Station Phase 3 21Nov09
PROVISION OF HARBOUR TUGS, PILOT BOATS AND MOORING GANGS 15Nov09
Supply, Design and Construction Works for New Liquefied Gas Filling Plant Project (Umm Al Aish) - Kuwait Oil Tanker Company 25Jan10
Shah Gas Field - Main Process Package 31Dec09
Shah Gas Field - Development Package 31Dec09
Construction of New Booster Station BS-171 at West Kuwait. 09Feb10
SSO PROJECT FOR QP 08Nov09
SUPPLY & COMMISSION - TRAILERISED AIR CONVEYANCE SYSTEM FOR OIL SPILL OPERATION. 09Nov09
Upgrading of Basic Infrastructure for Information Technology & Communication Network for Kuwait Petroleum Corporation - Kuwait Petroleum Corporation 13Dec09
CALL-OFF CONT FOR MACH., BAL. & METAL SPRAY AT QP VARI. LOCS 22Nov09
FEED FOR NEW 16" JET A1 P/L FROM QP REFINERY TO BSV3 08Nov09
EPIC OF PRIVACY & BREAKWATER WALL AT DWS FACILITY, DUKHAN 06Dec09
Shah Gas Field - Offsite Package 31Dec09
Oracle Program Licensing - KUWAIT PETROLEUM CORPORATION 01Dec09
 »  More Tenders
 
 
 
Community Buzz

Stories

Companies

Most viewed companies by Community in the last 24 hrs
Company Name Country Industry
Consolidated Contractors Company Overseas Construction and Design
Saudi Binladin Group Saudi Arabia Construction and Design
Saudi Electricity Company Saudi Arabia Electric Utilities
Saudi Telecom Saudi Arabia Telecommunications Services
Emirates Telecommunications Corporation UAE Telecommunications Services
Sharjah Electricity and Water Authority UAE Electric Utilities
Al Azizia Panda United Company Saudi Arabia General Retailers
Hyundai Engineering and Construction Company - Saudi Arabia Saudi Arabia Construction and Design
National Commercial Bank Saudi Arabia Banking
Commercial International Bank (Egypt) Egypt Banking
 

Projects

Most viewed projects by Community in the last 24 hrs
Project Name Country Sector
Takreer - Ruwais Refinery Expansion UAE Oil and Gas
Al Futtaim Carillion - Marina Hotel (Yas Island) UAE Real Estate
Emirates Aluminium (EMAL) - Smelter Complex - Phase 1 UAE Industry
Abu Dhabi DOT - Abu Dhabi Metro UAE Infrastructure
SATORP - Jubail Refinery and Petrochemical Complex Saudi Arabia Oil and Gas
ENEC - Nuclear Power Plant UAE Power and Water
Dubai RTA - Dubai Metro UAE Infrastructure
Al Safwa - Jeddah Cement Plant Saudi Arabia Industry
Qatar Bahrain Causeway Foundation - Qatar Bahrain Causeway Qatar Infrastructure
Qatar Bahrain Causeway Foundation - Qatar Bahrain Causeway Bahrain Infrastructure
 

Blogs

 
 

 
 
 
 
 

Site is optimised for viewing at 1024 x 768 with Internet Explorer v6 and Firefox v3.0 and above.
Copyright © 2009 ABQ Zawya Ltd. All rights reserved. Please read our Membership Agreement