Schon Properties Affirms Refunds

Press Release
 
 

Developers Finalising Contract for Remaining Zones with Leading Contractor

Dubai, UAE, 20 August, 2008; Schon PropertiesSchon PropertiesLoading..., developer of the AED 3 billion Dubai Lagoon project, has confirmed that full refunds will be given to all investors that purchased units scheduled for completion by December 2007. The refund policy has been extended by SchonSchonLoading... as an act of goodwill after confusion amongst some investors in regards to the project phases and revised completion dates.

Delays in completion of Dubai Lagoon have been the direct result of unanticipated civic and transportation infrastructure alterations, which have set back construction and produced scheduling issues. "We at Sch?n Properties applaud and fully support the efforts of RTA and other government agencies to make Dubai a better place and we have re-designed our project to accommodate mandatory infrastructure developments imposed subsequent to the launch of the Dubai Lagoon," said Nasir Husain, Co-Chairman of Schon PropertiesSchon PropertiesLoading....

SchonSchonLoading... has been in discussions with RERA to clarify the situation and reach a fair solution for all parties. Whilst not common practice in the UAE, the revised refund policy was approved by SchonSchonLoading... Board of Directors during a board meeting held on Tuesday 19th August, to accommodate investors and demonstrate good faith. Investors, who purchased units with a completion date of December 2007, are eligible for a full refund and are directed to apply for this prior to September 15th 2008.

In a recent statement about Schon PropertiesSchon PropertiesLoading... and the Dubai Lagoon, Marwan Bin Ghalaita, CEO of RERA, characterized the objections of some investors as "a misunderstanding". He said, "Schon [Properties]Schon [Properties]Loading... is a registered developer with us and they have an open trust account and all the money from the Dubai Lagoon [project] is in trust account handled by the Land Department and RERA. Furthermore, RERA issued a press release earlier this week dismissing reports that the project had been cancelled and pledging continued involvement and monitoring of construction works.

SchonSchonLoading... has also confirmed that the agreement with the original contractors Powerline Gulf has been renegotiated to include the first two zones and construction is due resume in the coming weeks. The first zone is now set for completion within 13 months and the second zone is set for completion within 18 months as of July 28th. Negotiations with another leading contractor to handle the remaining zones are currently being finalised of which official appointments by SchonSchonLoading... will be announced shortly.

"While certain investors are understandably frustrated and upset by the delays, the vast majority have demonstrated great understanding and patience and have expressed confidence in Schon PropertiesSchon PropertiesLoading... and support for the Dubai Lagoon project. It is not in the best interest of any parties involved with the project, including developers to delay construction, as material costs are exponentially rising. Therefore we are aiming to deliver the project in the timeliest manner given the unforeseen circumstances," concluded Husain.

-Ends-

For More Information, please contact:
Mohamed Osman
Media Coordinator
Schon PropertiesSchon PropertiesLoading... Limited,
Telephone: +971 4 321 9503
Fax: +971 3 3219507
pr@schonproperties.com

Mahmoud Fansa
Account Manager
TRACCS Public Relations
Telephone: +971 4 3672530
Fax: +971 4 3672531
mahmoud.fansa@traccs.net

© Press Release 2008 from TRACCS

 
Share this on:        Delicious         Digg         reddit         Facebook         StumbleUpon
 
 
 
 
Community Comments (0) - Comment on this article
The opinions of the authors expressed herein do not necessarily state or reflect Zawya. Read our Comment Policy.
 
 
 
Loading ...
 
Loading ...
Zawya Comment Policy:
 
  1. Zawya encourages you to add a comment to this discussion. You agree that when you add content to this discussion your comments will not:
    1.1   Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
    1.2   Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
    1.3   Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
    1.4   Be threatening, abuse or invade another’s privacy, or cause annoyance, inconvenience or needless anxiety.
    1.5   Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
    1.6   Give the impression that they represent Zawya.
    1.7   Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse.
  2. The content posted on www.zawya.com is created by members of the public. The views expressed are theirs and unless specifically stated are not those of Zawya. Zawya reserves the right to review all comments prior to posting and edit or delete any contribution, but Zawya is not responsible for and can not be held liable for any content posted by members of the public on www.zawya.com.
  3. Zawya is not responsible for the availability or content of any third party sites that are accessible through www.zawya.com. Any links to third party websites from www.zawya.com do not amount to any endorsement of that site by Zawya and any use of that site by you is at your own risk.
  4. By submitting your comment, you hereby give Zawya the right, but not the obligation, to post, air, edit, exhibit, telecast, webcast, re-use, publish, reproduce, use, license, print, distribute or otherwise use your comments worldwide, in perpetuity.
 
 
 
Community Buzz

Stories

Companies

Most viewed companies by Community in the last 24 hrs
Company Name Country Industry
Consolidated Contractors Company Overseas Construction and Design
Abu Dhabi Investment Council UAE Investment Firms and Funds
Dubai Islamic Bank UAE Banking
Saudi Electricity Company Saudi Arabia Electric Utilities
Saudi Binladin Group Saudi Arabia Construction and Design
Qatar Investment Authority Qatar Investment Firms and Funds
Jazeera Airways Kuwait Transportation Services
Al Rajhi Investment Group Saudi Arabia Investment Firms and Funds
Kuwait Telecommunications Company Kuwait Telecommunications Services
Saudi Arabian Oil Company Saudi Arabia Oil
 

Projects

Most viewed projects by Community in the last 24 hrs
Project Name Country Sector
Dubai RTA - Dubai Metro - Purple Line UAE Infrastructure
IPIC - Abu Dhabi Crude Oil Pipeline (ADCOP) UAE Oil and Gas
Emirates Aluminium (EMAL) - Smelter Complex UAE Industry
Qatar Foundation - Sidra Hospital Qatar Real Estate
Ras Tanura Integrated Refinery and Petrochemicals Complex Saudi Arabia Oil and Gas
KNPC - Al Zour Refinery Kuwait Oil and Gas
Qatalum Aluminum Smelter Qatar Industry
Abu Dhabi Municipality - Salam Street and Mina Road Development UAE Infrastructure
Nakheel - Dubai Waterfront UAE Real Estate
ADCO - SAS Field Development UAE Oil and Gas
 

Blogs

 
 

 
 
 
 
 
Quote data provided by © TickerChart
Site is optimised for viewing at 1024 x 768 with Internet Explorer v6 and Firefox v1.5 and above.
Copyright © 2008 ABQ Zawya Ltd. All rights reserved. Please read our Membership Agreement