Heir Apparent opens Dolphin Project

The Peninsula
 
 
13 May 2008
Doha - The Heir Apparent H H Sheikh Tamim bin Hamad Al Thani along with the Crown Prince of Abu Dhabi and Deputy Supreme Commander of the UAE, Sheikh Mohammed bin Zayed Al Nahyan yesterday opened the Dolphin EnergyDolphin EnergyLoading...'s gas processing plant, the world's largest single-build gas plant at Ras Laffan Industrial CityRas Laffan Industrial CityLoading....

The opening ceremony marked the successful completion of the $4.8bn Dolphin Gas Project - the largest gas initiative ever undertaken in the region. The seven-year construction programme has seen the creation of a full energy value chain-from gas wells offshore Qatar, onshore processing plant, gas export pipeline to the UAE and substantial gas supplies to customers across the seven Emirates.

Dolphin EnergyDolphin EnergyLoading...'s major strategic initiative, the Dolphin Project, involves the production and processing of natural gas from Qatar's North Field, an transportation of the dry gas by sub-sea export pipeline from Qatar to the UAE, which began last year.

The long-term customers for Dolphin gas from Qatar include the Abu Dhabi Water and Electricity AuthorityAbu Dhabi Water and Electricity AuthorityLoading..., the Union Water and Electricity AuthorityUnion Water and Electricity AuthorityLoading..., the Dubai Supply Authority and from the third quarter of this year Oman Oil Company. Each has signed a gas supply agreement with Dolphin EnergyDolphin EnergyLoading... for 25 years. The Heir Apparent H H Sheikh Tamim bin Hamad Al Thani and the Crown Prince of Abu Dhabi and Deputy Supreme Commander of the UAE armed forces Sheikh Mohammed bin Zayed Al Nahyan opened the Dolphin EnergyDolphin EnergyLoading...'s gas processing plant at Ras Laffan Industrial CityRas Laffan Industrial CityLoading... yesterday. A folk troupe in Qatari, Emirati and Omani national costumes performing at the opening ceremony. (QASSIM RAHMATULLAH)

Dolphin EnergyDolphin EnergyLoading... is owned 51 percent by Mubadala Development Company, on behalf of the Government of Abu Dhabi and 24.5 percent each by Total of France and Occidental Petroleum of the USA.

The overall investment in constructing the entire Dolphin Gas Project, which includes 24 wells, 2 production platforms, twin sealines, processing plant, export pipelines, processing plant, export pipelines and receiving facilities totaled over $4.8bn. Dolphin is already supplying up to two billion standard cubic feet (scf/day) of refined natural gas per day to UAE.

Dolphin EnergyDolphin EnergyLoading... CEO, Ahmed Ali Al Sayegh said: "Today we reiterate our long term focus and vision: Dolphin is a major source of clean, new energy for the Southern Gulf and a catalyst for the region's economic growth."

© The Peninsula 2008

 
 
 
Community Comments (0) - Comment on this article
The opinions of the authors expressed herein do not necessarily state or reflect Zawya. Read our Comment Policy.
 
 
 
Loading ...
 
Report Abuse
Loading ...
 
 
Loading ...
Zawya Comment Policy:
 
  1. Zawya encourages you to add a comment to this discussion. You agree that when you add content to this discussion your comments will not:
    1.1   Contain any material which is libelous or defamatory of any person, is obscene, offensive, hateful or inflammatory or causes damage to the reputation of any person or organisation.
    1.2   Promote sexually explicit material, violence, discrimination based on race, sex, religion, nationality, disability, sexual orientation or age or any illegal activity.
    1.3   Be made in breach of any legal duty owed to a third party, such as a contractual duty or a duty of confidence.
    1.4   Be threatening, abuse or invade another's privacy, or cause annoyance, inconvenience or needless anxiety.
    1.5   Be used to impersonate any person, to misrepresent your identity or affiliation with any person, or be likely to deceive any person.
    1.6   Give the impression that they represent Zawya.
    1.7   Advocate, promote or assist any unlawful act such as (by way of example only) copyright infringement or computer misuse.
  2. The content posted on www.zawya.com is created by members of the public. The views expressed are theirs and unless specifically stated are not those of Zawya. Zawya reserves the right to review all comments prior to posting and edit or delete any contribution, but Zawya is not responsible for and can not be held liable for any content posted by members of the public on www.zawya.com.
  3. Zawya is not responsible for the availability or content of any third party sites that are accessible through www.zawya.com. Any links to third party websites from www.zawya.com do not amount to any endorsement of that site by Zawya and any use of that site by you is at your own risk.
  4. By submitting your comment, you hereby give Zawya the right, but not the obligation, to post, air, edit, exhibit, telecast, webcast, re-use, publish, reproduce, use, license, print, distribute or otherwise use your comments worldwide, in perpetuity.
 
 
 
 
 
 
 
Post Your Tender Notices for FREE
(No Sign-in Required)
 
 
Oil and Gas Tenders Due Date
Supply, Design and Construction Works for New Liquefied Gas Filling Plant Project (Umm Al Aish) - Kuwait Oil Tanker Company 25Jan10
On Plot Construction Contract for Amal Steam Surface Facilities 07Feb10
Foodstuff Supply - KUWAIT PETROLEUM CORPORATION 08Nov09
IMPLEMENTATION OF MISC. PLANT CHANGE REQUESTS(PCRS) at HALUL 15Nov09
Off Plot Construction Contract for Amal Steam Surface Facilities 07Feb10
Supply of Chemicals for three Company Refineries - Kuwait National Petroleum Company 08Dec09
UPGRADE OF UPS SYSTEMS,BATTERY CHARGERS&BATTERY BANKS AT NFA 29Nov09
Installation, Operation & Maintenance of Integrated Security System for all company facilities consisting of Two Parts, Part A: Installation and Part B: Provision of Support, Operation & Maintenance 27Nov09
PRICE AGREEMENT FOR ELECTRICAL CABLES. 20Dec09
Maintenance of Photocopiers and Accessories - KUWAIT PETROLEUM CORPORATION 06Dec09
Oracle Program Licensing - KUWAIT PETROLEUM CORPORATION 01Dec09
First Project EF/1713 : Construction of Oil and Gas Pipelines at Mina Al Ahmadi To Subiya and Doha Power Stations Second Project EF/1760 : Construction of Pumping Station and Oil and Gas Pipelines at Mina Al Ahmadi To Al Zoor and Shuaiba Power Stations 07Feb10
Provision of Catering Services and Related Services for KPC Employees Training Program - KUWAIT PETROLEUM CORPORATION 01Dec09
Supply of Computers and Provision of Technical Support Package - Kuwait Petroleum Corporation 13Dec09
EPIC OF PROVIDING LIGHTING FOR SHELVES IN STORE 51, GAS OPER 09Nov09
Qarn Alam Power Station Phase 3 21Nov09
HOOK UP OF FLOWLINE,PWI & GASLIFT WELLS 13Dec09
PROVISION OF FUEL & MAINT OF FUEL OUTLETS (Tentative Bid Due Date and award date) 28Jan10
Mabruk Oil Operations (MOO) invites interested local and international companies (or their representatives) specialized in providing Drilling Fluids Services to submit to MOO their completed Pre-qualification documents, for evaluation and preparation of a bidders list, as MOO intends shortly to issue a Call for Tender for Drilling Fluids Services for its Offshore Al-Jurf Oil Field. 31Dec09
Maintenance Works for Outdoor Plants and Irrigation Systems - KUWAIT PETROLEUM CORPORATION 01Dec09
 »  More Tenders
 
 
 
Community Buzz

Stories

Companies

Most viewed companies by Community in the last 24 hrs
Company Name Country Industry
Consolidated Contractors Company Overseas Construction and Design
Saudi Binladin Group Saudi Arabia Construction and Design
Saudi Telecom Saudi Arabia Telecommunications Services
Saudi Electricity Company Saudi Arabia Electric Utilities
Emirates Aluminium Company UAE Metal Production
Sharjah Electricity and Water Authority UAE Electric Utilities
Emirates Telecommunications Corporation UAE Telecommunications Services
Al Azizia Panda United Company Saudi Arabia General Retailers
Commercial International Bank (Egypt) Egypt Banking
Dodsal Engineering and Construction UAE Construction and Design
 

Projects

Most viewed projects by Community in the last 24 hrs
Project Name Country Sector
Takreer - Ruwais Refinery Expansion UAE Oil and Gas
Al Futtaim Carillion - Marina Hotel (Yas Island) UAE Real Estate
Emirates Aluminium (EMAL) - Smelter Complex - Phase 1 UAE Industry
Abu Dhabi DOT - Abu Dhabi Metro UAE Infrastructure
ENEC - Nuclear Power Plant UAE Power and Water
SATORP - Jubail Refinery and Petrochemical Complex Saudi Arabia Oil and Gas
Dubai RTA - Dubai Metro UAE Infrastructure
Al Safwa - Jeddah Cement Plant Saudi Arabia Industry
Qatar Bahrain Causeway Foundation - Qatar Bahrain Causeway Bahrain Infrastructure
Qatar Bahrain Causeway Foundation - Qatar Bahrain Causeway Qatar Infrastructure
 

Blogs

 
 

 
 
 
 
 

Site is optimised for viewing at 1024 x 768 with Internet Explorer v6 and Firefox v3.0 and above.
Copyright © 2009 ABQ Zawya Ltd. All rights reserved. Please read our Membership Agreement